Order created on Jan 31, 2026
Order value
$163,120.00
Freight cost
$1,562.49
Duty
$100,123.07
Amount paid
$79,441.67
Production
Order confirmed on Jan 31, 2026. The 30% deposit ($79,441.67) was paid on Feb 17; the remaining 70% is planned for Apr 11 before shipment. Production is at 29%—500 units completed, 3,000 in progress, 2,500 pending. Estimated completion and due date is Apr 25, 2026. Order is currently in inbound process.
| Article | Qty | Unit FOB price | HTS | Subtotal | Duty % | Duty | Total cost |
|---|---|---|---|---|---|---|---|
| 6,000 | $27.19 | 7323.93.00.45 | $163,120.00 | 61.38% | $100,123.07 | $263,243.07 | |
| TOTAL | 6,000 | $263,243.07 | |||||
Payment terms
Net 30 Days
Incoterm
–
Scheduled payments
Total items
6,000
Completed
500
In progress
3,000
Pending
2,500
Completed %
8%
Est. date
4/25/26
Progress by products 1 articles 6,000 total units
| Product | Variants | Units | Progress | Status |
|---|---|---|---|---|
| 12 variants | 6000 units | 29% | Concluded |